Water main renewal will lead to six months’ traffic disruption to Chamberlayne Road

image-2 

Here are the details from Brent Council’s website. Use this link to find updates on Road works, closures and diversions.
  
18/1/16 – 12/2/16 – Chamberlayne Road will be closed between the junction of Kilburn Lane and Banister Road, large scale diversions including HGVs will be in place and buses will be rerouted to suitable routes.
15/2/16 – 11/3/16 – Banister Road will be closed at the junction of Chamberlayne Road, large scale diversions including HGV’s will be in place and Buses will be rerouted to suitable routes. Traffic on Chamberlayne Road will be controlled using two way temporary signals.
22/2/15 – 27/3/16 – Hardinge Road, Leighton Gardens and Okehampton Road will be closed at the junction of  Chamberlayne Road to allow traffic to be controlled using two way temporary signals.
28/3/16 – 15/4/16 – Mortimer Road and Harvist Road will be closed at the junction of Chamberlayne Road to allow traffic to be controlled using two way temporary signals.
15/4/16 – mid July – Works will progress north towards Okehampton Road, traffic will be controlled using two way temporary signals, the maximum length of the site will be 75m, side roads will be closed where required
 
Thanks to Ric Smith for pointing out that QPARA members and Harvist Road residents should be made aware that during the closure of Banister Road (mid Feb to mid march) 3 bus routes will be diverted to run along Harvist Road. #6 #187 #316.Diversions detailed here https://www.brent.gov.uk/services-for-residents/transport-and-streets/road-works-closures-and-diversions/